Utilities: build the backbone once, add modules with the presses; four-module boiler hall and chiller compound
Deploy test site / deploy (push) Successful in 57s
Deploy test site / deploy (push) Successful in 57s
Phased build list for steam, cooling and hydraulics (launch, Duplex 1, Duplex 2, Classic, options): everything cheap to oversize and costly to retrofit (rooms, pads, headers and ring mains with a valved branch per press position, tanks, HX frame, feeders, one sequencer) is built for the five-press fleet at launch; boilers, chillers and hydraulic pump sets come in identical modules as presses arrive. The Single 2.1 aggregate is proposed as the first central pump set; per-branch isolation and filters. Rooms sized for four modules each (user decision, estimates until vendor footprints): boiler hall ~18 x 9 m for four 500 kg/h positions (fired case, AIX DZL0.5 body), open screened chiller compound ~12.5 x 10.8 m with four pads (250 kW at 40 C ~ Carrier 30RB 080-090), ~40 m2 pump and HX room; the cooling tower pad of the water-cooled concept is dropped. Yard 178 -> ~379 m2. Four boilers carry ~8 presses with N+1; four 250 kW chillers carry the five presses with CH-4 as reserve and no growth position unless the pads take the ~350 kW frame (RFQ option). - scale.md: yard table and basis, utility phasing section - pressing-line.md: hydraulics phasing and re-quote questions - steam-cooling.html: B-4 position, phasing and rooms card, details, RFQ questions (pw_sc_check clean) - construction RFQ: yard table, sealed area 6,549 m2 (68 %) - total-investment: added-scope row +73k to +122k USD (building rate on the ~200 m2 the yard grows by) - Payap parts model: yard rebuilt from Params (blr_n, blr_inst, ch_*, bh_*, cy_*, pr_*), renders updated
This commit is contained in:
1 parent
7688d03be6
commit
e49abf89d3
8 files changed
+163
-29
No files matched your search
+91
-11
@@ -92,20 +92,63 @@ fits; at the upper half, finished goods move to the phase 2 building.
|
||||
The massing model puts the boiler and chiller in a **detached utility yard**
|
||||
alongside the main building rather than inside it, which is what the boiler's
|
||||
own-room requirement in [facility security](facility-security.md) and biomass
|
||||
fuel delivery both push toward:
|
||||
fuel delivery both push toward. Its rooms are built once for **four boiler
|
||||
and four chiller modules** (decided October 2026), while the modules
|
||||
themselves arrive one press stage at a time
|
||||
([utility phasing](#utility-phasing-backbone-once-modules-with-the-presses)):
|
||||
|
||||
| | Area | Height |
|
||||
|---|---|---|
|
||||
| Boiler hall | 66 m² | 6.0 m |
|
||||
| Boiler hall, four 500 kg/h module positions | ~162 m² (18 × 9 m) | 6.0 m |
|
||||
| Biomass fuel store | 42 m² | 5.0 m |
|
||||
| Chiller room | 60 m² | 5.0 m |
|
||||
| Cooling tower (outdoor pad) | 10 m² | 3.5 m |
|
||||
| Chiller compound, four 250 kW pads, open to the sky, screened | ~135 m² (12.5 × 10.8 m) | screen ~2.5 m |
|
||||
| Cooling pump and heat-exchanger room | ~40 m² (8 × 5 m) | 4.0 m |
|
||||
| Flue stack | - | 14 m |
|
||||
|
||||
Boiler plus chiller at 126 m² lands inside the 100 to 150 m² the zone table
|
||||
allows, but moving them out of the main shed frees that floor for
|
||||
production, so either the main building shrinks by ~126 m² or the program
|
||||
grows into it. Decide which before the building is priced.
|
||||
All sizes are estimates until the boiler and chiller vendors send
|
||||
footprints:
|
||||
|
||||
- **Boiler hall.** The fuel is still open, so the fired case sets the
|
||||
size. The largest piece of a 500 kg/h biomass boiler is about
|
||||
3.3 × 2.0 × 2.7 m (AIX DZL0.5 listing, checked October 2026). Four
|
||||
3.5 m bays plus a 4 m bay for the feed tank, softener, feed pumps and
|
||||
steam header make 18 m. A 2.5 m firing aisle, 1.5 m of fuel feed, the
|
||||
boiler and 1.3 m behind it make 9 m. Dust collectors, fans and the stack
|
||||
stand outside along the back wall. An electric bank (~3.0 × 1.5 m per
|
||||
500 kg/h module, vendor listing) would need about half the hall.
|
||||
- **Chillers.** Air-cooled chillers need open air, so the earlier
|
||||
"chiller room" becomes an open, screened compound plus a small enclosed
|
||||
room for the heat exchanger, the cold tank and the pumps. A 250 kW
|
||||
module rated at 40 °C is about the size of a Carrier 30RB 080 to 090:
|
||||
2.4 to 3.6 × 2.24 × 2.28 m (Carrier's published dimensions, checked
|
||||
October 2026). The pads are 4.0 × 2.6 m, in two rows of two, with
|
||||
~1.8 m to the screen and 2.0 m between the rows; the chosen unit's
|
||||
clearance drawing governs. The cooling tower pad of the earlier
|
||||
water-cooled concept is gone; a dry cooler, if bought, gets a pad sized
|
||||
with its quote.
|
||||
- **What four positions carry.**
|
||||
- Steam: four boilers give 2,000 kg/h, or 1,500 kg/h with one held in
|
||||
reserve, enough for about eight presses at 180 kg/h. The five-press
|
||||
fleet runs on B-1 and B-2, B-3 is the reserve, and B-4 is room for
|
||||
about three more presses.
|
||||
- Cooling: four chillers give 1,000 kW. The five presses (~652.5 kW)
|
||||
already need three, so CH-4 is the reserve and there is no growth
|
||||
position. Each further press adds ~130 kW with its extruder and
|
||||
hydraulics; a sixth eats into the reserve, and seven is the limit with
|
||||
none.
|
||||
- Pads laid out for the next frame up (Carrier 30RB 120 to 150 class,
|
||||
~4.8 m long, roughly 350 kW at 40 °C, estimate) would let four
|
||||
chillers carry about eight presses with one in reserve, matching the
|
||||
boiler hall. That is a priced option for the chiller RFQ.
|
||||
|
||||
The yard grows from 178 m² to ~379 m². The old 126 m² of boiler hall and
|
||||
chiller room fitted the 100 to 150 m² the zone table allows for them in the
|
||||
main building; the four-module rooms would not, which is one more reason the
|
||||
yard stays detached. Moving the plant out frees that zone-table floor for
|
||||
production, so either the main building shrinks by that much or the program
|
||||
grows into it. Decide which before the building is priced. The
|
||||
[Payap parts model](site-candidates.md#roof-pv-and-parking-canopies-part-and-draft-model-october-2026)
|
||||
draws the yard this way.
|
||||
|
||||
Staff parking is roofed, in the front yard clear of the loading route:
|
||||
**10 car bays** (27.7 × 7.0 m canopy, 195 m²) and **~30 scooter spaces**
|
||||
@@ -240,12 +283,13 @@ small against the connection, but its own feeder and meter.
|
||||
180 °C** (~510 to 610 kW thermal) at Newbilt's 150 to 180 kg/h per press.
|
||||
Proposed: **two 500 kg/h modules** (B-1 with the launch press and Duplex
|
||||
system 1, B-2 with system 2 and the Classic), 1,000 kg/h installed; a
|
||||
third module for N+1 is an RFQ option
|
||||
([steam and cooling](steam-cooling.html)). The 2024 Newbilt quote's
|
||||
third module for N+1 is an RFQ option, and the hall has a fourth position
|
||||
for growth ([steam and cooling](steam-cooling.html)). The 2024 Newbilt quote's
|
||||
~400 kg/h covers one Duplex system
|
||||
- Chiller bank: up to **~650 kW** of cooling; proposed **three 250 kW
|
||||
air-cooled modules** rated at 40 °C ambient, one per press stage, behind a
|
||||
plate heat exchanger with warm and cold tanks (estimate)
|
||||
plate heat exchanger with warm and cold tanks (estimate); the compound's
|
||||
fourth pad takes the N+1 module
|
||||
- If biomass: **~350 to 400 t/yr** air-dry wood at ~1.0 to 1.1 million
|
||||
records a year, up to **~550 t/yr** at the start fleet's full ~1.5
|
||||
million (fuel follows records pressed, not presses installed); the 60 rai
|
||||
@@ -253,6 +297,42 @@ small against the connection, but its own feeder and meter.
|
||||
- If LPG: a bulk tank on site sized with the boiler bank (the ~2.5 to 5 t
|
||||
first estimated was for one Duplex; no gas pipeline in the North)
|
||||
|
||||
### Utility phasing: backbone once, modules with the presses
|
||||
|
||||
The plant starts with one press. Everything that is cheap to oversize now
|
||||
and costly to change in a running plant is built for the five-press fleet
|
||||
at launch; the machines that make steam, cold water and oil pressure are
|
||||
bought in identical modules as presses arrive. Identical modules mean one
|
||||
set of spares and one service routine, and N+1 later is one more module,
|
||||
not a redesign.
|
||||
|
||||
| Stage | Steam | Cooling | Hydraulics and air |
|
||||
|---|---|---|---|
|
||||
| Launch: Newbilt Single 2.1, one press | Boiler hall for four modules; T-1, WT-1, P-1; steam main and condensate return with a valved, blanked branch at every press position; **B-1** | Compound with four pads; TK-2 and TK-3 at full size; HX-1 frame for ~650 kW with plates for the launch duty; P-2 to P-4 on VFDs; supply and return mains for ~540 l/min with a valved branch per position; **CH-1** | Plant room at full size; hydraulic and air ring mains along the service trench, sized for the fleet, with a valved, capped tee per position; the Single 2.1's own unit in the plant room as the first pump set on the manifold; one compressor |
|
||||
| Duplex system 1 complete (second press, EX 35) | B-1 at 60 to 72 % load | CH-1 covers ~96 % of the hot-afternoon peak (~261 kW): the cold tank and cycle overlap carry the rest, or CH-2 comes forward if the hot season arrives first | Tap the ring main; the Single 2.1 unit is already sized for the second press |
|
||||
| Duplex system 2 | **B-2** | **CH-2** | A pump set added on the manifold; a second compressor if the air demand needs it |
|
||||
| Classic | Carried by B-1 and B-2 | **CH-3** | A pump set, if the Classic runs from the central plant (Newbilt re-quote) |
|
||||
| Options | **B-3** (N+1); **B-4** for about three more presses; ACC-1 accumulator; ECON-1 on a fired bank | **CH-4** (N+1); TC-1 dry cooler; pads for the ~350 kW frame | A standby pump set, or the Single 2.1 unit as standby |
|
||||
|
||||
Also built at launch: one controller that sequences the boilers, chillers
|
||||
and pump sets lead and lag from the first module, and switchboard space and
|
||||
feeders for every later module. Beyond four modules, the ten optional
|
||||
Classics (~2.3 to 2.7 t/h, ~1.9 MW) are a utility phase of their own, on
|
||||
reserved ground with its own header connection.
|
||||
|
||||
Two things to watch early:
|
||||
|
||||
- A fired 500 kg/h boiler serving one press runs at ~30 to 36 % and cycles.
|
||||
Newbilt's steam accumulator (ACC-1) steadies it; or the first module is
|
||||
electric and biomass follows at the expansion ([biomass](biomass.md)),
|
||||
at the price of the demand charge.
|
||||
- One large boiler or chiller bought at launch would run poorly at part
|
||||
load, tie up capital in unused capacity and stop the plant when it fails.
|
||||
|
||||
The hydraulic side and its re-quote questions are in
|
||||
[pressing line](equipment/pressing-line.md); the plant diagram and its
|
||||
operating cases in [steam and cooling](steam-cooling.html#phasing).
|
||||
|
||||
## People
|
||||
|
||||
Rough mature-operation headcount (estimate): 4 to 6 press/finishing
|
||||
|
||||
Reference in new issue