Utilities: build the backbone once, add modules with the presses; four-module boiler hall and chiller compound
Deploy test site / deploy (push) Successful in 57s

Phased build list for steam, cooling and hydraulics (launch, Duplex 1,
Duplex 2, Classic, options): everything cheap to oversize and costly to
retrofit (rooms, pads, headers and ring mains with a valved branch per
press position, tanks, HX frame, feeders, one sequencer) is built for the
five-press fleet at launch; boilers, chillers and hydraulic pump sets come
in identical modules as presses arrive. The Single 2.1 aggregate is
proposed as the first central pump set; per-branch isolation and filters.

Rooms sized for four modules each (user decision, estimates until vendor
footprints): boiler hall ~18 x 9 m for four 500 kg/h positions (fired case,
AIX DZL0.5 body), open screened chiller compound ~12.5 x 10.8 m with four
pads (250 kW at 40 C ~ Carrier 30RB 080-090), ~40 m2 pump and HX room; the
cooling tower pad of the water-cooled concept is dropped. Yard 178 -> ~379
m2. Four boilers carry ~8 presses with N+1; four 250 kW chillers carry the
five presses with CH-4 as reserve and no growth position unless the pads
take the ~350 kW frame (RFQ option).

- scale.md: yard table and basis, utility phasing section
- pressing-line.md: hydraulics phasing and re-quote questions
- steam-cooling.html: B-4 position, phasing and rooms card, details, RFQ
  questions (pw_sc_check clean)
- construction RFQ: yard table, sealed area 6,549 m2 (68 %)
- total-investment: added-scope row +73k to +122k USD (building rate on
  the ~200 m2 the yard grows by)
- Payap parts model: yard rebuilt from Params (blr_n, blr_inst, ch_*,
  bh_*, cy_*, pr_*), renders updated
This commit is contained in:
grabowski committed 2026-10-14 21:02:30 +07:00
1 parent 7688d03be6
commit e49abf89d3
8 files changed
+163 -29

No files matched your search

+91 -11
View File
@@ -92,20 +92,63 @@ fits; at the upper half, finished goods move to the phase 2 building.
The massing model puts the boiler and chiller in a **detached utility yard**
alongside the main building rather than inside it, which is what the boiler's
own-room requirement in [facility security](facility-security.md) and biomass
fuel delivery both push toward:
fuel delivery both push toward. Its rooms are built once for **four boiler
and four chiller modules** (decided October 2026), while the modules
themselves arrive one press stage at a time
([utility phasing](#utility-phasing-backbone-once-modules-with-the-presses)):
| | Area | Height |
|---|---|---|
| Boiler hall | 66 m² | 6.0 m |
| Boiler hall, four 500 kg/h module positions | ~162 m² (18 × 9 m) | 6.0 m |
| Biomass fuel store | 42 m² | 5.0 m |
| Chiller room | 60 m² | 5.0 m |
| Cooling tower (outdoor pad) | 10 m² | 3.5 m |
| Chiller compound, four 250 kW pads, open to the sky, screened | ~135 m² (12.5 × 10.8 m) | screen ~2.5 m |
| Cooling pump and heat-exchanger room | ~40 m² (8 × 5 m) | 4.0 m |
| Flue stack | - | 14 m |
Boiler plus chiller at 126 m² lands inside the 100 to 150 m² the zone table
allows, but moving them out of the main shed frees that floor for
production, so either the main building shrinks by ~126 m² or the program
grows into it. Decide which before the building is priced.
All sizes are estimates until the boiler and chiller vendors send
footprints:
- **Boiler hall.** The fuel is still open, so the fired case sets the
size. The largest piece of a 500 kg/h biomass boiler is about
3.3 × 2.0 × 2.7 m (AIX DZL0.5 listing, checked October 2026). Four
3.5 m bays plus a 4 m bay for the feed tank, softener, feed pumps and
steam header make 18 m. A 2.5 m firing aisle, 1.5 m of fuel feed, the
boiler and 1.3 m behind it make 9 m. Dust collectors, fans and the stack
stand outside along the back wall. An electric bank (~3.0 × 1.5 m per
500 kg/h module, vendor listing) would need about half the hall.
- **Chillers.** Air-cooled chillers need open air, so the earlier
"chiller room" becomes an open, screened compound plus a small enclosed
room for the heat exchanger, the cold tank and the pumps. A 250 kW
module rated at 40 °C is about the size of a Carrier 30RB 080 to 090:
2.4 to 3.6 × 2.24 × 2.28 m (Carrier's published dimensions, checked
October 2026). The pads are 4.0 × 2.6 m, in two rows of two, with
~1.8 m to the screen and 2.0 m between the rows; the chosen unit's
clearance drawing governs. The cooling tower pad of the earlier
water-cooled concept is gone; a dry cooler, if bought, gets a pad sized
with its quote.
- **What four positions carry.**
- Steam: four boilers give 2,000 kg/h, or 1,500 kg/h with one held in
reserve, enough for about eight presses at 180 kg/h. The five-press
fleet runs on B-1 and B-2, B-3 is the reserve, and B-4 is room for
about three more presses.
- Cooling: four chillers give 1,000 kW. The five presses (~652.5 kW)
already need three, so CH-4 is the reserve and there is no growth
position. Each further press adds ~130 kW with its extruder and
hydraulics; a sixth eats into the reserve, and seven is the limit with
none.
- Pads laid out for the next frame up (Carrier 30RB 120 to 150 class,
~4.8 m long, roughly 350 kW at 40 °C, estimate) would let four
chillers carry about eight presses with one in reserve, matching the
boiler hall. That is a priced option for the chiller RFQ.
The yard grows from 178 m² to ~379 m². The old 126 m² of boiler hall and
chiller room fitted the 100 to 150 m² the zone table allows for them in the
main building; the four-module rooms would not, which is one more reason the
yard stays detached. Moving the plant out frees that zone-table floor for
production, so either the main building shrinks by that much or the program
grows into it. Decide which before the building is priced. The
[Payap parts model](site-candidates.md#roof-pv-and-parking-canopies-part-and-draft-model-october-2026)
draws the yard this way.
Staff parking is roofed, in the front yard clear of the loading route:
**10 car bays** (27.7 × 7.0 m canopy, 195 m²) and **~30 scooter spaces**
@@ -240,12 +283,13 @@ small against the connection, but its own feeder and meter.
180 °C** (~510 to 610 kW thermal) at Newbilt's 150 to 180 kg/h per press.
Proposed: **two 500 kg/h modules** (B-1 with the launch press and Duplex
system 1, B-2 with system 2 and the Classic), 1,000 kg/h installed; a
third module for N+1 is an RFQ option
([steam and cooling](steam-cooling.html)). The 2024 Newbilt quote's
third module for N+1 is an RFQ option, and the hall has a fourth position
for growth ([steam and cooling](steam-cooling.html)). The 2024 Newbilt quote's
~400 kg/h covers one Duplex system
- Chiller bank: up to **~650 kW** of cooling; proposed **three 250 kW
air-cooled modules** rated at 40 °C ambient, one per press stage, behind a
plate heat exchanger with warm and cold tanks (estimate)
plate heat exchanger with warm and cold tanks (estimate); the compound's
fourth pad takes the N+1 module
- If biomass: **~350 to 400 t/yr** air-dry wood at ~1.0 to 1.1 million
records a year, up to **~550 t/yr** at the start fleet's full ~1.5
million (fuel follows records pressed, not presses installed); the 60 rai
@@ -253,6 +297,42 @@ small against the connection, but its own feeder and meter.
- If LPG: a bulk tank on site sized with the boiler bank (the ~2.5 to 5 t
first estimated was for one Duplex; no gas pipeline in the North)
### Utility phasing: backbone once, modules with the presses
The plant starts with one press. Everything that is cheap to oversize now
and costly to change in a running plant is built for the five-press fleet
at launch; the machines that make steam, cold water and oil pressure are
bought in identical modules as presses arrive. Identical modules mean one
set of spares and one service routine, and N+1 later is one more module,
not a redesign.
| Stage | Steam | Cooling | Hydraulics and air |
|---|---|---|---|
| Launch: Newbilt Single 2.1, one press | Boiler hall for four modules; T-1, WT-1, P-1; steam main and condensate return with a valved, blanked branch at every press position; **B-1** | Compound with four pads; TK-2 and TK-3 at full size; HX-1 frame for ~650 kW with plates for the launch duty; P-2 to P-4 on VFDs; supply and return mains for ~540 l/min with a valved branch per position; **CH-1** | Plant room at full size; hydraulic and air ring mains along the service trench, sized for the fleet, with a valved, capped tee per position; the Single 2.1's own unit in the plant room as the first pump set on the manifold; one compressor |
| Duplex system 1 complete (second press, EX 35) | B-1 at 60 to 72 % load | CH-1 covers ~96 % of the hot-afternoon peak (~261 kW): the cold tank and cycle overlap carry the rest, or CH-2 comes forward if the hot season arrives first | Tap the ring main; the Single 2.1 unit is already sized for the second press |
| Duplex system 2 | **B-2** | **CH-2** | A pump set added on the manifold; a second compressor if the air demand needs it |
| Classic | Carried by B-1 and B-2 | **CH-3** | A pump set, if the Classic runs from the central plant (Newbilt re-quote) |
| Options | **B-3** (N+1); **B-4** for about three more presses; ACC-1 accumulator; ECON-1 on a fired bank | **CH-4** (N+1); TC-1 dry cooler; pads for the ~350 kW frame | A standby pump set, or the Single 2.1 unit as standby |
Also built at launch: one controller that sequences the boilers, chillers
and pump sets lead and lag from the first module, and switchboard space and
feeders for every later module. Beyond four modules, the ten optional
Classics (~2.3 to 2.7 t/h, ~1.9 MW) are a utility phase of their own, on
reserved ground with its own header connection.
Two things to watch early:
- A fired 500 kg/h boiler serving one press runs at ~30 to 36 % and cycles.
Newbilt's steam accumulator (ACC-1) steadies it; or the first module is
electric and biomass follows at the expansion ([biomass](biomass.md)),
at the price of the demand charge.
- One large boiler or chiller bought at launch would run poorly at part
load, tie up capital in unused capacity and stop the plant when it fails.
The hydraulic side and its re-quote questions are in
[pressing line](equipment/pressing-line.md); the plant diagram and its
operating cases in [steam and cooling](steam-cooling.html#phasing).
## People
Rough mature-operation headcount (estimate): 4 to 6 press/finishing