Solar and battery re-priced from Thai market data (October 2026)
Deploy test site / deploy (push) Successful in 46s
Deploy test site / deploy (push) Successful in 46s
- Rooftop PV, 300 kWp (size still illustrative): 20 to 26 THB/W installed with the Deye hybrid inverters, 6.0M to 7.8M THB (was 25 to 35 THB/W, 7.5M to 10.5M). Sources in the utilities CSV: DEDE Thailand PV Status report (Mahidol survey: 22 to 25 THB/W for factory systems of 10 kW to 1 MW, 2023), CapSolar 2026 (20 to 25 under 1 MWp), Saimai Solar's list (300 kW for 5.4M THB), Deye hybrid inverter retail (160,500 THB per 50 kW). - Battery 271 kWh, now installed: 2.0M to 3.5M THB (was the bare Gobel list price, 1.4M to 2.0M, which matches DEDE's 5,000 to 7,000 THB/kWh for LiFePO4); adds enclosure, fire protection, controls and installation, below CapSolar's 12,000 to 15,000 THB/kWh for a fully installed factory BESS because the hybrid inverters do the conversion (estimate). - Utilities baseline 27.57M to 47.50M THB; launch plant ~160M / 222M / 283M THB with contingency; Plan B ~208M (~149M to 266M), ~31M more than Plan A; Plan A's total unchanged, its solar lever ~9.7M. PV payback ~3.8 to 5.4 years (sustainability.md). Calculator, README, roadmap, revenue model and both business plan versions (renders included) updated.
This commit is contained in:
1 parent
3f33babdaa
commit
ab303618d8
25 files changed
+116
-111
No files matched your search
@@ -367,13 +367,14 @@ def blocks():
|
||||
"Taken through a solar PPA (below): the plant pays the PPA price for this "
|
||||
"power instead of buying the array, so its saving is the gap between that "
|
||||
"price and the ~3.7 THB/kWh of grid power it displaces",
|
||||
"Saves ~1.2M to 1.3M THB a year and pays back in ~4.5 to 7 years at 25,000 "
|
||||
"to 35,000 THB/kWp (estimates)")],
|
||||
"Saves ~1.2M to 1.3M THB a year and pays back in ~3.8 to 5.4 years at 20,000 "
|
||||
"to 26,000 THB/kWp installed (estimates)")],
|
||||
["Canopies and the second building", "~40 kWp on the parking canopies (construction RFQ; ~54 "
|
||||
"kWp if fully covered). A phase 2 building's roof adds "
|
||||
"~251 kWp, ~498 kWp across both roofs"],
|
||||
["Battery", "271 kWh Gobel Power LiFePO4 rack (15 stacked 18 kWh packs, 8,000+ cycles), USD "
|
||||
"39,900 to 58,000 listed, 50 to 60 day lead. Roughly an hour of the chiller bank's "
|
||||
"39,900 to 58,000 listed (battery only; ~2.0M to 3.5M THB installed with enclosure, fire protection and "
|
||||
"controls, estimate), 50 to 60 day lead. Roughly an hour of the chiller bank's "
|
||||
"peak draw: ride-through, not off-grid autonomy"],
|
||||
["Inverters", "Deye three-phase hybrid units (30 to 80 kW class), Thai distribution via Solar "
|
||||
"Nicolo; Deye is a supported protocol on the Gobel battery management"],
|
||||
@@ -387,17 +388,18 @@ def blocks():
|
||||
"terms", "")],
|
||||
pick(["Solar PPA (this plan)", "An installer owns and finances the PV and the battery, and the "
|
||||
"plant buys the power at a price still to quote (the calculator carries 3.0 THB/kWh, an "
|
||||
"estimate, ~0.03M USD a year on the energy line). That keeps the PV EPC (USD 227k to "
|
||||
"318k) and the battery (USD 42k to 62k) out of the capital round: ~10.7M THB less at the "
|
||||
"estimate, ~0.03M USD a year on the energy line). That keeps the PV EPC (USD 182k to "
|
||||
"236k) and the battery (USD 61k to 106k) out of the capital round: ~9.7M THB less at the "
|
||||
"midpoint, one of the six levers in section 8. The BOI solar measure (section 7) rewards "
|
||||
"the plant's own solar investment, so its tax value very likely goes with the array (to "
|
||||
"confirm with the BOI consultant). The PPA offer is asked against the specification "
|
||||
"above"],
|
||||
["Owned (this plan)", "The plant buys the array and the battery: rooftop PV EPC USD 227k "
|
||||
"to 318k (7.5M to 10.5M THB) and the battery USD 42k to 62k (1.4M to 2.0M THB), "
|
||||
["Owned (this plan)", "The plant buys the array and the battery: rooftop PV EPC USD 182k "
|
||||
"to 236k (6.0M to 7.8M THB, 20 to 26 THB/W at Thai 2026 market prices) and the battery, installed, "
|
||||
"USD 61k to 106k (2.0M to 3.5M THB), "
|
||||
"estimates, section 8. Owning them is what the BOI solar measure rewards (section 7). A "
|
||||
"solar PPA (an installer owns and finances them, the plant buys the power at a price "
|
||||
"still to quote) would take ~10.7M THB out of the capital round at the midpoint, but "
|
||||
"still to quote) would take ~9.7M THB out of the capital round at the midpoint, but "
|
||||
"very likely gives up that measure"]),
|
||||
]),
|
||||
H3("Steam: the open engineering choice"),
|
||||
@@ -965,7 +967,7 @@ def blocks():
|
||||
P("**Process:** file via the e-Investment system and present at an analyst meeting. BOI quotes "
|
||||
"about 40 working days to a decision for projects under THB 200M and 60 to 90 working days for "
|
||||
"larger tiers; at " + pick("~127M to 226M THB with the ramp-up reserve (~177M at the midpoint)",
|
||||
"~150M to 268M THB with the ramp-up reserve (~209M at the midpoint)") +
|
||||
"~149M to 266M THB with the ramp-up reserve (~208M at the midpoint)") +
|
||||
" the plan sits around that line, so the consultant "
|
||||
"confirms which applies. In practice it is roughly 4 to 6 months end to end to the certificate; "
|
||||
"the company is incorporated under it; machinery is imported within a window commonly 30 months "
|
||||
|
||||