Solar (user, 17 Oct 2026: "use as much roof space as possible") - PV on every roof and canopy: ~640 kWp on the Payap scenario plot (factory roof ~523, canopies ~54, flat office roof ~65 kWp around the AC units); ~300 kWp on the Mueang Chi hall. Calculator: pvKWp 640, new pvSelf 85 % (zero export, hourly sketch), PV cost per kWp times the array, office-roof PV in the iso view, roofs drawn full. - 12.8M to 16.6M THB at 20 to 26 THB/W; CSV baseline 34.37M to 56.34M; launch plant ~168M / 231M / 294M THB with contingency; Plan B ~216M (label ~215M), ~39M above Plan A; Plan A unchanged (it leases the array), its solar lever ~17.5M. PV payback ~4.2 to 5.9 years. - Permits (rooftop solar no factory licence since 28 Dec 2024, ERC exemption under 1,000 kVA, PEA zero export) and PPA discounts sourced in sustainability.md. BOI correction - Announcement 3/2568 (in force 1 July 2025) ended BOI promotion for solar installations; only the battery may qualify (12M THB per MW cap). Removed the "BOI solar measure" from boi.md, total-investment, revenue-model, sustainability, site-candidates and both plan versions; Plan B's case for owning the array is the PPA bill it avoids (~0.07M USD a year). Open source (user, 17 Oct 2026) - digital-factory.md "Open source throughout, and working with other plants": everything we run and build is open source on NixOS, our code published (licence to decide), vendor firmware the stated exception; later the stack and factory-automation services for other pressing plants, not in the revenue. - Business plan section 5.6 plus an executive-summary bullet, reading guide and not-modelled mentions; draft 0.3 rebuilt (A 60, B 61 pages), renders re-made with the roofs full.
This commit is contained in:
1 parent
ab303618d8
commit
9ff5feef11
32 files changed
+693
-367
No files matched your search
+26
-12
@@ -15,13 +15,25 @@ no corporate income tax holiday on the core pressing activity, but the full
|
||||
non-tax package and machinery duty exemption. The tax value is engineered on
|
||||
top through the upgrade measures, where this project happens to be strong:
|
||||
|
||||
- **Solar and battery**: the alternative-energy measure (Announcement
|
||||
2/2568, April 2025, under the Smart and Sustainable Industry framework)
|
||||
grants CIT exemption based on the solar investment. Eligible spend
|
||||
explicitly includes PV modules, inverters, BESS and BESS inverters, and
|
||||
mounting structures, capped at THB 12M/30M/40M of investment value per MW
|
||||
depending on investment type. The planned Deye + Gobel installation
|
||||
converts directly into CIT-exemption headroom.
|
||||
- **Solar: no longer promoted; the battery may be.** The alternative-energy
|
||||
measure (Announcement 2/2568, April 2025, under the Smart and Sustainable
|
||||
Industry framework) granted a CIT exemption on the solar investment,
|
||||
capped at THB 12M/30M/40M per MW. **Announcement 3/2568** (5 June 2025,
|
||||
in force 1 July 2025) ended promotion for installing solar power
|
||||
generation under that measure for applications from 1 July 2025; what
|
||||
remains is machinery modified to use other renewable energy, and battery
|
||||
storage (BESS) with its inverters, the eligible investment capped at
|
||||
THB 12M per MW
|
||||
([B Global Law](https://bgloballaw.com/2026/01/18/boi-announcement-no-3-2568-amendment-to-renewable-energy-efficiency-enhancement-measures),
|
||||
[Smarter Energy Solution](https://smarterenergysolution.com/blog/boi-solar-thailand-2026),
|
||||
checked October 2026). So owning the ~640 kWp array earns no BOI
|
||||
benefit; its case is the bill (see [sustainability](sustainability.md)).
|
||||
Whether the 271 kWh battery qualifies is for the BOI consultant. A PPA
|
||||
developer selling solar power (200 kW or more per distribution point)
|
||||
can still be promoted under activity 7.1.2 (8-year CIT exemption); that
|
||||
benefit is the developer's, and how much of it reaches the PPA price is
|
||||
a negotiation
|
||||
([CapSolar](https://capsolar.co.th/en/knowledge/boi-solar-incentives-2026)).
|
||||
- **Automation and metrology**: the Smart and Sustainable Industry upgrade
|
||||
measure (Announcement 15/2565, refreshed July 2025) rewards automation,
|
||||
smart machinery, and energy efficiency, typically 3 years of CIT
|
||||
@@ -33,8 +45,8 @@ top through the upgrade measures, where this project happens to be strong:
|
||||
galvanics process development, and recycled-PVC work could be framed as
|
||||
qualifying development.
|
||||
|
||||
So the application is pitched on solar, automation, and technology content,
|
||||
not on "we press plastic discs."
|
||||
So the application is pitched on automation and technology content (and
|
||||
the battery, if it qualifies), not on "we press plastic discs."
|
||||
|
||||
## What Group B still delivers (the core value)
|
||||
|
||||
@@ -119,11 +131,13 @@ project timeline, ahead of equipment contracts.
|
||||
|
||||
- Confirm the exact activity sub-code and tier for vinyl/PVC consumer-goods
|
||||
pressing (Group B assumption is well supported but not code-verified)
|
||||
- Confirm the live versions and per-MW caps of the solar and
|
||||
smart-and-sustainable measures at filing time
|
||||
- Confirm the live version of the smart-and-sustainable measures at
|
||||
filing time, and whether the battery qualifies under the BESS part of
|
||||
the alternative-energy measure (THB 12M per MW cap); solar itself is out
|
||||
since 1 July 2025 (Announcement 3/2568)
|
||||
- Confirm current NEC/Lamphun area add-ons
|
||||
- Engage a BOI-registered consultant to structure the application so the
|
||||
solar, automation, and R&D measures stack on the base promotion
|
||||
automation and R&D measures (and the battery) stack on the base promotion
|
||||
- Check whether R&D contracted with Payap University and the joint student
|
||||
programmes ([Payap partnership](payap-partnership.md)) count toward the
|
||||
R&D merit or a skills-development measure
|
||||
|
||||