Biomass steam in both plans, PV on the factory roof only
Deploy test site / deploy (push) Successful in 49s

User, 17 Oct 2026: "only put solar on the factory, prepare the other
buildings for solar, option a and b should operate on biomass".

- Steam: two 500 kg/h biomass modules (Getabec class, 6M to 10M THB) plus
  a fuel store and handling block (1M to 2M, estimate) in both plans; the
  electric bank becomes the alternative. ~0.67M THB of fuel a year against
  ~4.9M for electric steam; grid demand ~264 kW instead of ~980 kW.
- Solar: ~520 kWp on the factory roof (the biomass-case optimum is ~500 to
  550 kWp, hourly sketch in sustainability.md "PV size with biomass
  steam"); office roof and parking canopies built PV-ready (~120 kWp
  later). ~87 % used on site, ~61 % of the plant's electricity.
- Calculator: biomass default, bFuel row, pvKWp 520, pvSelf 87, iso fills
  the factory roof first and shows the other roofs as PV-ready.
- Numbers: launch plant ~168M / 232M / 296M with contingency; Plan A
  ~182M (~2M above 180M: the Chinese-route lever priced only electric
  boilers; a Chinese biomass quote is the way back), Plan B ~217M (label
  ~215M), ~35M more. Calculator EBITDA A 2.17M, B 2.23M USD.
- CSV, total-investment, revenue-model, sustainability, scale, biomass,
  site-candidates, boi, steam-cooling, construction RFQ (canopies
  PV-ready), README, roadmap; business plan draft 0.3 rebuilt (A and B
  63 pages) with new renders.
This commit is contained in:
grabowski committed 2026-10-17 20:24:55 +07:00
1 parent 9ff5feef11
commit 984ced2485
35 files changed
+849 -665

No files matched your search

+1 -1
View File
@@ -173,7 +173,7 @@ Nothing in Phases 2 to 5 starts before its gate clears: no machinery order
before the BOI certificate, no big-block spending before the market
validates the price, no coppice fuel planning before the land title check.
Since October 2026 the plant launches with everything in one capital
round (~168M to 294M THB with contingency; for the investor Plan A at
round (~168M to 296M THB with contingency; for the investor Plan A at
~180M and Plan B at ~215M THB without it, in
[total investment](finance/total-investment.md#two-plans-a-at-180m-thb-and-b-at-215m-thb-october-2026));
the gates still come before the round is spent, and the growth options