Biomass steam in both plans, PV on the factory roof only
Deploy test site / deploy (push) Successful in 49s
Deploy test site / deploy (push) Successful in 49s
User, 17 Oct 2026: "only put solar on the factory, prepare the other buildings for solar, option a and b should operate on biomass". - Steam: two 500 kg/h biomass modules (Getabec class, 6M to 10M THB) plus a fuel store and handling block (1M to 2M, estimate) in both plans; the electric bank becomes the alternative. ~0.67M THB of fuel a year against ~4.9M for electric steam; grid demand ~264 kW instead of ~980 kW. - Solar: ~520 kWp on the factory roof (the biomass-case optimum is ~500 to 550 kWp, hourly sketch in sustainability.md "PV size with biomass steam"); office roof and parking canopies built PV-ready (~120 kWp later). ~87 % used on site, ~61 % of the plant's electricity. - Calculator: biomass default, bFuel row, pvKWp 520, pvSelf 87, iso fills the factory roof first and shows the other roofs as PV-ready. - Numbers: launch plant ~168M / 232M / 296M with contingency; Plan A ~182M (~2M above 180M: the Chinese-route lever priced only electric boilers; a Chinese biomass quote is the way back), Plan B ~217M (label ~215M), ~35M more. Calculator EBITDA A 2.17M, B 2.23M USD. - CSV, total-investment, revenue-model, sustainability, scale, biomass, site-candidates, boi, steam-cooling, construction RFQ (canopies PV-ready), README, roadmap; business plan draft 0.3 rebuilt (A and B 63 pages) with new renders.
This commit is contained in:
1 parent
9ff5feef11
commit
984ced2485
35 files changed
+849
-665
No files matched your search
+1
-1
@@ -26,7 +26,7 @@ top through the upgrade measures, where this project happens to be strong:
|
||||
THB 12M per MW
|
||||
([B Global Law](https://bgloballaw.com/2026/01/18/boi-announcement-no-3-2568-amendment-to-renewable-energy-efficiency-enhancement-measures),
|
||||
[Smarter Energy Solution](https://smarterenergysolution.com/blog/boi-solar-thailand-2026),
|
||||
checked October 2026). So owning the ~640 kWp array earns no BOI
|
||||
checked October 2026). So owning the ~520 kWp factory-roof array earns no BOI
|
||||
benefit; its case is the bill (see [sustainability](sustainability.md)).
|
||||
Whether the 271 kWh battery qualifies is for the BOI consultant. A PPA
|
||||
developer selling solar power (200 kW or more per distribution point)
|
||||
|
||||