Payap still an option: rezoning route; order example opaque
Deploy test site / deploy (push) Successful in 2m40s

User, 20 Oct 2026: Payap University claims they can rezone the land;
update the deck to show it is still an option. And: do not use a
transparent vinyl as the example in the order tool screenshot.

- land-listings/payap/rezoning-2026-10-20.md (new): what a rezoning is
  under the Town Planning Act B.E. 2562 (section 35 amendment started by
  DPT or the local official, Town Planning Commission, 30-day posting
  with objections, Ministry of Interior notification via Cabinet and the
  Royal Gazette; a landowner can ask, not rezone), the DPT's own work
  plan (~70 weeks without objections, ~82 with: ~16 to 19 months), the
  schedule effect (roughly a year on first production unless the request
  starts now; estimate) and what to ask Payap. DPT procedure PDF filed.
- site-candidates.md: Payap "still an option" in the table, rezoning
  paragraph with an Open action, check 1 and the re-siting rule; zoning
  record, payap-partnership.md and README point to it.
- Business plan 6.1, risk table and critical path: Payap's rezoning
  claim and its ~16 to 19 months; A and B rebuilt (63 pages, checked).
- Deck: site slide names Payap as an option once rezoned, notes and
  source line; risk row updated.
- order.html: the "Splatter 12"" preset now has a white base instead of
  clear; deck platform screenshots re-shot in both themes (numbers
  unchanged: 100 fans, break-even 46, ~480 THB kept). Order checks 96/96,
  fan parity 206/206; deck verify clean in both themes, PDFs rebuilt.
This commit is contained in:
grabowski committed 2026-10-20 14:58:40 +07:00
1 parent 744a56d22b
commit 967e6b1c76
20 files changed
+171 -17

No files matched your search

+3 -1
View File
@@ -54,7 +54,9 @@ open.
with write access to production systems.
- **Location.** On Payap land the plant and the classroom share a campus;
at Mueang Chi they are ~35 km apart. The programme works better with the
Payap site but need not depend on it.
Payap site but need not depend on it. The first Payap plot needs
rezoning, which Payap says it can obtain (20 October 2026; what that
takes: [site candidates](site-candidates.md#payap-university-new-lead-october-2026)).
- **BOI.** R&D contracted with a Thai university and training cooperation
may count toward the R&D merit measure; an open item in [BOI](boi.md).