Payap still an option: rezoning route; order example opaque
Deploy test site / deploy (push) Successful in 2m40s
Deploy test site / deploy (push) Successful in 2m40s
User, 20 Oct 2026: Payap University claims they can rezone the land; update the deck to show it is still an option. And: do not use a transparent vinyl as the example in the order tool screenshot. - land-listings/payap/rezoning-2026-10-20.md (new): what a rezoning is under the Town Planning Act B.E. 2562 (section 35 amendment started by DPT or the local official, Town Planning Commission, 30-day posting with objections, Ministry of Interior notification via Cabinet and the Royal Gazette; a landowner can ask, not rezone), the DPT's own work plan (~70 weeks without objections, ~82 with: ~16 to 19 months), the schedule effect (roughly a year on first production unless the request starts now; estimate) and what to ask Payap. DPT procedure PDF filed. - site-candidates.md: Payap "still an option" in the table, rezoning paragraph with an Open action, check 1 and the re-siting rule; zoning record, payap-partnership.md and README point to it. - Business plan 6.1, risk table and critical path: Payap's rezoning claim and its ~16 to 19 months; A and B rebuilt (63 pages, checked). - Deck: site slide names Payap as an option once rezoned, notes and source line; risk row updated. - order.html: the "Splatter 12"" preset now has a white base instead of clear; deck platform screenshots re-shot in both themes (numbers unchanged: 100 fans, break-even 46, ~480 THB kept). Order checks 96/96, fan parity 206/206; deck verify clean in both themes, PDFs rebuilt.
This commit is contained in:
1 parent
744a56d22b
commit
967e6b1c76
20 files changed
+171
-17
No files matched your search
@@ -299,7 +299,8 @@ def _risk_rows():
|
||||
"months would push launch to mid-2029; Pheenix, Sillitoe and Sibert lead times also unquoted",
|
||||
"Required field in every re-quote, now"],
|
||||
["High", "Zoning of the chosen plot unverified", "A site reset costs ~6 months; the Payap point "
|
||||
"already fails zoning; Mueang Chi is unverified", "Verify on the land-use map and with counsel "
|
||||
"fails zoning as the plan stands (Payap says it can be rezoned: ~16 to 19 months); Mueang Chi is "
|
||||
"unverified", "Verify on the land-use map and with counsel "
|
||||
"before the BOI filing; industrial estate as "
|
||||
"fallback"],
|
||||
]
|
||||
@@ -932,7 +933,8 @@ def blocks():
|
||||
], widths_mm=[10, 68, 34, 58]),
|
||||
T(["Track (in parallel)", "Needed by", "Float", "Becomes critical if"], [
|
||||
["Land lease, zoning, soil test", "Design start, ~Q1 2027", "~4 months", "Zoning fails and a new "
|
||||
"site is needed (~6 months reset); the plot Payap first offered already fails zoning"],
|
||||
"site is needed (~6 months reset); the plot Payap first offered fails zoning unless the rezoning "
|
||||
"Payap describes is gazetted (~16 to 19 months)"],
|
||||
["Construction, incl. the water-treatment building and utility yard", "Machinery arrival, "
|
||||
"~Q3 2028", "~3 to 5 months", "Soft soil forces piling, or permits stall; the galvanics room, "
|
||||
"clean zone and ZLD plant are now needed first, ahead of the press hall"],
|
||||
|
||||