BOI: machinery import duty and import VAT, PVC duty relief
Deploy test site / deploy (push) Successful in 35s

User, October 2026: take the BOI duty-free import and VAT exemption into
consideration.

- boi.md: import VAT goes with the BOI duty exemption (Revenue Department
  answer on the BOI OSOS FAQ, checked October 2026); what it is worth:
  ~2.75M USD of imported machinery at the start fleet (block midpoints)
  would otherwise carry ~5 % duty (Thai MFN averages 4.1 % on HS 8477,
  0 to 10 % across HS 84; estimate until the HS codes are set), ~0.14M
  USD, and 7 % import VAT, ~0.2M paid at the border and recovered later
  as input tax, mostly as a refund claim since exports are zero-rated.
- total-investment.md: the blocks are vendor prices without duty or
  import VAT, so the headline already assumes promotion.
- Fleet calculator: BOI promoted / not promoted switch and export share.
  Not promoted adds the machinery duty to capex and depreciation, shows the
  import VAT as cash at the border, and charges duty on imported PVC
  compound; promoted exempts both, with no compound duty on exported
  records and 90 % off for domestic sales (sections 36(1) and 30). A note
  under the KPIs shows what promotion saves either way. Defaults: payback
  3.1 years with BOI, 3.2 without; adverse case operating result -31k
  with BOI, -68k without. CIT and BOI CIT exemptions still not modelled.
This commit is contained in:
grabowski committed 2026-10-10 20:29:32 +07:00
1 parent 1a368287f8
commit 8032e0ea47
4 files changed
+68 -11

No files matched your search

+4 -1
View File
@@ -75,7 +75,10 @@ exactly this reason.
- **BOI**: machinery duty exemption applies across most of the equipment
blocks, and the solar and automation spend converts into CIT-exemption
headroom; the application precedes every purchase order (see
[boi.md](../boi.md))
[boi.md](../boi.md)). The blocks are vendor prices without Thai duty or
import VAT, so the headline assumes promotion: without it, ~0.14M USD of
duty and ~0.2M USD of import VAT (reclaimable later) come on top at the
start fleet (estimate)
- **Buy vs lease** on land and building swings roughly **1.0M to 2.1M
USD (~34M to 69M THB)** of upfront capital, and also moves the launch
date by about three quarters — see