Plant view: toilets in the factory, link lands on doors, no separate trimmer
Deploy test site / deploy (push) Successful in 45s

User feedback on the isometric view (October 2026):
- "the production hall is missing toilets": two sets. At the staff
  entry: women 2 WC, men 1 WC and 1 urinal, an accessible WC, basins.
  At the east end of the back aisle in the finishing block: women 2 WC,
  men 1 WC and 1 urinal, basins (proposed, not yet in the parametric
  plans). site-candidates.md gets a Toilets bullet with the Thai minimum
  (Ministerial Regulation No. 39 B.E. 2537, table 2; separate toilets for
  men, women and disabled staff under the welfare regulation B.E. 2548).
- "the door and the corridor is not aligned": the covered link now lands
  on doors at both ends, centred on it (factory entrance at the start of
  the visitor corridor, office lobby door on the north face, windows
  cleared); the corridor glass starts after the door; the stray staff
  door with no path is gone; the link deck ramps up to the factory floor.
- "we also dont need a extra trimmer with the optical, this is included
  in the duplex and the classics": the finishing block keeps only the
  optical inspection station; site-candidates.md, the tour route and the
  process flow say the presses trim inline.

Checks: renderer 720 checks and functional checks pass (max 2,485 SVG
nodes); calculator regression 0 fails; level selector works in the page;
no page errors or overflow at 390 / 1024 / 1440 px, dark and light.
This commit is contained in:
grabowski committed 2026-10-16 19:40:05 +07:00
1 parent 8e4559ee36
commit 4beda7f27a
4 files changed
+83 -34

No files matched your search

+25 -6
View File
@@ -161,7 +161,8 @@ and every equipment envelope is an estimate.
- **Factory, production floor only**: 128 × 25 m at floor level +1.2 m,
16 frame bays, in process order along a 98 m glazed visitor corridor.
From west to east:
- staff entry (PPE, WC);
- staff entry (PPE and toilets), reached from the start of the visitor
corridor where the covered link from the office lands;
- workshop and spares, with the machine door and a 12 m vehicle ramp
at the north-west corner;
- the galvanics clean room with a chemical day store, open to stamper
@@ -191,9 +192,13 @@ and every equipment envelope is an estimate.
- **Finishing and print block**, 14 × 25 m on two levels, beyond the
end of the crane runway
([plans](cnx_vinyl_parametric_payap-block.png)).
- Ground floor: trim and optical inspection, the QC lab, and
packaging (~170 m²) with packing tables, shrink wrap and a pallet
wrapper next to the fire shutter into the warehouse.
- Ground floor: optical inspection, the QC lab, and packaging
(~170 m²) with packing tables, shrink wrap and a pallet wrapper next
to the fire shutter into the warehouse. There is no separate
trimmer: every Duplex cell and the Classic trim inline
([pressing line](equipment/pressing-line.md)). Toilets for women
and men close the end of the back aisle in the north-east corner
(proposed October 2026, not yet in the plans).
- Upper floor at +3.8 m: a print room kept in reserve (in-house
printing is not decided; jackets come from a print partner today,
[production timeline](production-timeline.md)), the print stock
@@ -205,6 +210,20 @@ and every equipment envelope is an estimate.
and a small CNC mill among the tools
([crane, workshop and tours](crane-workshop-tours.md)).
- The 5 t crane runs from the west wall to the end of the press hall.
- **Toilets** in two sets, so nobody on the floor is more than about
50 m from one (layout estimate): at the staff entry (women 2 WC, men
1 WC and 1 urinal, an accessible WC, basins) and at the east end of
the back aisle in the finishing block (women 2 WC, men 1 WC and 1
urinal, basins). For a factory, Ministerial Regulation No. 39
(B.E. 2537) under the Building Control Act, table 2, asks per up to
15 workers of each sex for: men 1 WC, 1 urinal, 1 bathroom and 1
basin; women 2 WC, 1 bathroom and 1 basin
([text](https://www.bsa.or.th/%E0%B8%81%E0%B8%8E%E0%B8%AB%E0%B8%A1%E0%B8%B2%E0%B8%A2/%E0%B8%81%E0%B8%8E%E0%B8%81%E0%B8%A3%E0%B8%B0%E0%B8%97%E0%B8%A3%E0%B8%A7%E0%B8%87-%E0%B8%89%E0%B8%9A%E0%B8%B1%E0%B8%9A%E0%B8%97%E0%B8%B5%E0%B9%88-39-%E0%B8%9E%E0%B8%A8-2537.html)).
The labour welfare regulation (B.E. 2548) asks for separate toilets
for men, women and disabled staff
([summary](https://thailawyers.com/labour-welfare-in-thailand)). A
shift stays under 15 of each ([scale](scale.md#people)), and the
showers are in the office changing rooms.
- **PVC silos** (proposed), outside on the north side of the lane:
- two for black, two for standard colours, ~50 m³ each (estimate);
- a big-bag filling station;
@@ -227,8 +246,8 @@ and every equipment envelope is an estimate.
acoustic lining, the listening room and the archive (mobile shelving
on the ground slab, [facility security](facility-security.md#archive-room-mobile-shelving)).
Staff change here
before crossing to the factory, whose staff entry keeps only PPE and a
WC.
before crossing to the factory, whose staff entry keeps only PPE and
toilets.
- First floor: the offices (~150 m²), a meeting and training room (the
[Payap programmes](payap-partnership.md)), a meeting room, the IT and
server room, toilets, a pantry, and a flexible room for a second