Payap model v2: bigger factory, shared plant room, separate water treatment
User, October 2026: the factory is too small and needs room to grow (possibly ten more Classics), one shared hydraulic and air supply, water treatment perhaps in a separate building connected to the galvanics lab, and a fully equipped workshop (maintenance tools, 3D printers, maybe a lathe and a small CNC mill). Model (rebuilt live in FreeCAD 26.3, BIM objects, Params-driven, parametric check plot 135->145 m and factory 112->120 m passed): - plot 135 m (11.4 rai) with a reserve; factory 112 x 25 m, 16 bays, 82 m visitor corridor, fire wall at 90 m; - press hall ~870 m2: two Duplex systems (EX 50 + EX 35), the Classic, ten future Classic positions in two rows on a service trench; - central hydraulics and compressed-air plant room (~62 m2); - water treatment building 12 x 10 m behind galvanics: buried duct (gravity from the +1.2 m floor), covered crossing 6 m clear; - workshop ~200 m2 with benches, tool cabinets, 3D printers, lathe, small CNC mill, drill, saw, welding bay, press, washer, measuring table. Docs: galvanics (water treatment building, proposed), crane doc (workshop fit-out; lathe and CNC mill not yet priced; corridor now 82 m), site-candidates Payap section rewritten, README bullet.
This commit is contained in:
1 parent
9e0c5d4045
commit
4263fbbd9b
7 files changed
+89
-40
No files matched your search
@@ -85,6 +85,15 @@ What this changes in the plan:
|
||||
[facility security](../facility-security.md) (no extraction, no
|
||||
plating) applies to every one.
|
||||
- Compressed air at 6 bar for the PASU; drains Ø32 mm.
|
||||
- **Water treatment in its own building (proposed, October 2026).** The
|
||||
zero-discharge effluent treatment, the DI water plant and the chemical
|
||||
store move out of the factory into a small building next to the
|
||||
galvanics room. A buried service duct carries the effluent by gravity
|
||||
from the galvanics floor at +1.2 m and brings DI water back, and a
|
||||
covered crossing joins the two doors. The galvanics room keeps only a
|
||||
chemical day store at the duct head. The
|
||||
[Payap scenario model](../site-candidates.md#payap-scenario-model-october-2026) draws it as a 12 × 10 m building
|
||||
(estimate).
|
||||
- **Space.** One of each unit is ~5.6 m² of footprint (PASU 1.56, PMPB
|
||||
1.23, PPPU 1.32, PDPU 1.44 m²), plus 500 mm service access behind the two
|
||||
tank units and working space around them: comfortably inside the 80 to
|
||||
|
||||