Rebase costs on USD/THB; add timelines and first market data
Currency - Base currency moves from EUR to USD and THB throughout. Rates at 5 Aug 2026: 1 USD = 33 THB, 1 EUR = 1.155 USD, 1 GBP = 1.35 USD. EUR/THB lands at ~38, so existing THB research needed no change. - Vendor quotes keep their original currency with a USD/THB equivalent alongside, so they stay checkable against the source PDFs. - Full vision ~4.7-8.9M USD; phased entry ~1.7-2.9M USD. New documents - production-timeline.md: order turnaround stage by stage. Launch 8-14 weeks, mature 5-10, repress 2-3. Quantifies the in-house galvanics turnaround claim the repo had asserted without a number, and flags artwork as an unmodelled fourth approval gate. - project-timeline.md: calendar to first paying release, ~Q4 2028. Critical path is BOI certificate to press order to build to commissioning. Two findings: Newbilt build time is absent from the repo yet carries ~40% of the schedule, and the BOI rule may be over-serialised since duty exemption attaches at importation rather than at contract signature. First market data (ResurRec, Bangkok) - Invoice-derived prices, a factory tour, and a confirmed fleet of one Newbilt Classic 12" automatic plus one semi-automatic. - Price ladder recorded at 300/500/1000-3000/3000+ units. Decomposes to roughly 34-50k THB fixed per title and 535-780 THB variable per unit, which is 4-7x the price this model assumes. - The incumbent presses 230-350k records/yr but buys every stamper as an import. That single constraint plausibly explains their 150-unit floor, their flat discount ladder and their large-run lead time, and it is what an in-house galvanics line attacks. Logged as an open question on whether galvanics should move from phase 5 to phase 1. - Inferences are marked as inferences; the whole set is one buyer and one plant, and the model is deliberately left unrebased until a second data point exists. Corrections - Gross margin arithmetic did not follow from its own inputs. Restated as ~1.95 USD at the midpoint with the 0.75-3.15 spread shown; the previous "40 to 55%" was not supported. - Direct cost low total 1.50 to 1.45 USD; contingency THB high 40M to 38M. - README indexes the construction RFQ, which was missing.
This commit is contained in:
1 parent
9d5d695855
commit
20c8d283d5
9 files changed
+946
-92
No files matched your search
@@ -25,7 +25,8 @@ The core semi-automatic machinery under evaluation comes from
|
||||
(scrap feeds back as the ~20% recycled share of the feedstock), 7" center
|
||||
label punch, buffer spindles and separator plates.
|
||||
|
||||
The June 2024 Newbilt quotation totals **≈ €200,500** including freight from
|
||||
The June 2024 Newbilt quotation totals **EUR 200,500** (about **USD 232k
|
||||
/ 7.7M THB** at August 2026 rates), including freight from
|
||||
Alsdorf to Thailand and seaworthy packaging. Two major utility systems are
|
||||
deliberately excluded and will be **sourced and installed locally in
|
||||
Thailand**: a ~400 kg/h steam generator (with water treatment) and a ~250 kW
|
||||
|
||||