# Project Scale: Rough Numbers One-page sizing of the whole project. Everything here is a planning estimate derived from the session's vendor data and standard ratios; figures marked "estimate" have no vendor confirmation yet. Update this page as real quotes and the site decision land. ## Production capacity | Phase | Fleet | Rough output | |---|---|---| | Launch | 1 semi-auto press (Newbilt Single), 1 shift | ~90,000 to 135,000 records/yr | | Duplex | 2 semi-auto presses, 1 to 2 shifts | ~300,000 to 600,000 records/yr | | Mature | 2 semi-auto + 2 automated (50/50 fleet), 2 shifts | ~1.0 to 1.5 million records/yr | Basis: the automated AD12 presses ~140 records/hour each (vendor datasheet); semi-automatic throughput is unpublished, assumed 60 to 80 records/hour per press with operator handling (estimate); 16 h/day, 300 days/yr, with realistic overall effectiveness of 60 to 70% applied. The theoretical ceiling of the mature fleet at 100% uptime is roughly 1.9 to 2.1 million records per year. ## Building | Zone | Rough area | |---|---| | Semi-auto press hall (Newbilt Duplex spec) | ~200 m² | | Automated press zone | ~100 to 150 m² | | Galvanics clean room + water treatment + chemical storage | ~80 to 150 m² | | Mastering and cutting room | ~40 to 60 m² | | Stamper prep | ~30 m² | | Packaging + finished goods warehouse | ~300 to 500 m² | | Utility rooms (boiler, compressor, chiller, electrical) | ~100 to 150 m² | | Offices, QC/listening, archive, IT, entrance | ~150 to 200 m² | | Circulation, walls, misc | ~150 to 250 m² | | **Total under roof** | **~1,200 to 1,700 m²** | The HVAC budget in the utilities CSV already assumes ~1,500 m² conditioned. Single story throughout: all heavy equipment needs ground-slab floor loading (multiple tons per m²). ## Land: factory plot Industrial plots typically allow 50 to 60% building coverage, and the site needs truck access and turning, parking, the outdoor cooling tower, the separated BESS enclosure, possible ground-mount solar, and expansion room. - Minimum workable: **~4 rai** (6,400 m²) - Comfortable with expansion and ground-mount solar: **~6 to 8 rai** (9,600 to 12,800 m²) Separate asset: the **60 rai** forestry-classified parcel for coppice fuelwood (see [biomass](biomass.md)), pending its title check. It is a fuel plantation, not a factory site candidate unless the classification allows conversion, which forestry land generally does not. ## Electrical scale | Load | Rough figure | |---|---| | Pressing machinery (semi-auto line + 2 automated presses) | ~70 to 80 kW installed | | Process chiller (250 kW cooling) | ~80 to 125 kW electrical | | Whole-factory HVAC | ~100 to 200 kW peak (estimate) | | Electric steam boiler (if chosen over biomass/LPG) | ~300 kW | | Compressed air, lighting, IT, misc | ~30 to 50 kW | | **Plant peak demand** | **~300 to 450 kW without electric boiler; ~600 to 750 kW with it** | Grid connection: a medium-voltage connection with a transformer in the **500 to 1,000 kVA** class from PEA, sized by the boiler decision. ## Solar and storage - Roof of a ~1,500 m² building fits roughly **150 to 200 kWp**; reaching the illustrative 300 kWp in the utilities CSV needs carport or ground-mount on the plot (about 1 rai of ground per additional 100 kWp, estimate) - Northern Thailand yield ~1,400 to 1,500 kWh/kWp/yr, so 300 kWp produces roughly **420 to 450 MWh/yr** - Plant consumption at mature two-shift operation: roughly **1,000 to 1,500 MWh/yr** without electric steam, up to **~2,500 MWh/yr** with it (estimate), so 300 kWp covers on the order of **20 to 35%** of consumption; a bigger array shifts that up - Battery: **271 kWh** Gobel stack (peak shaving and ride-through, roughly two to three hours of the chiller's electrical draw) ## Steam and fuel - Boiler: **400 kg/h at 10 bar / 180 °C** (~300 kW thermal) - If biomass: **~350 to 400 t/yr** air-dry wood at mature operation, of which the 60 rai coppice could supply **~80 to 135 t/yr** - If LPG: **~2.5 to 5 t** bulk tank on site (no gas pipeline in the North) ## People Rough mature-operation headcount (estimate): 4 to 6 press/finishing operators per shift, 2 to 3 galvanics, 1 to 2 mastering/cutting engineers, 1 to 2 QC, 2 maintenance, 3 to 5 admin/sales/logistics. Roughly **15 to 25 people** across shifts at maturity, fewer than half that at launch. ## Money (cross-references) - Newbilt semi-auto line: **~€200,500** (2024 quote, expired, in [pressing-line](equipment/pressing-line.md)) - Thai-sourced utilities, HVAC, racking, solar, BESS baseline: **~24M to 42M THB** (~€630k to 1.1M), detail in the [utilities CSV](finance/utilities-investment.csv) - Not yet priced: automated presses (indicative ~$340k each, unverified), galvanics line, mastering/cutting room, metrology, building construction/fit-out, land