Thai AI research
Contents

Where to build: a better data-center site than Chiang Mai

Research note, October 27, 2026, Alexander Grabowski (B4L). Sources retrieved October 27, 2026; figures are cited and our estimates marked.

This note looks for a data-center site with room for solar and possibly wind. It compares ten candidates with Chiang Mai and with the Eastern Economic Corridor (EEC), using our screening model, model/site_energy.py in the repository. The model matches hourly solar and wind output for 2019 to 2023 against 1 MW of IT at a PUE of 1.2, where PUE is total facility power divided by IT power. The building itself is described in option B. Money is in THB, with USD at 33 THB per USD, the B4L planning rate.

In short

What the site has to offer

Criterion What the site needs Basis
Land for solar About 100 rai per MW of IT for 10 MWp; 100 to 300 rai for 1 to 2 MW of IT plus the hall 5.001 MWp on about 50.6 rai in an ERC filing, about 10 rai per MWp[317]; installers quote 10 to 15 rai per MW[318]
Wind A sub-district with capacity factor 20% or more at 100 m, ideally beside existing farms JGSEE/NSTDA/EGAT ranking[307]
Grid An EGAT 115, 230 or 500 kV node within reach for later phases; the first 1 to 2 MW connects at 22 or 33 kV PEA normally supplies more than 10,000 kVA at 115 kV[290]
Fiber, Bangkok At least 4 telecom systems, 60 Gbps combined, for BOI; short distance to Bangkok BOI guide[319]; about 1.5 ms round trip per 100 km straight-line (our estimate: route factor 1.5, 5 microseconds per km)
Flood, earthquake No seismic zone; ground above historic floods 2021 seismic regulation[320]
Water Enough for a closed loop with spray on peak days; a water plan BOI condition[319]
Haze Fewer smoke days for filters and generator intakes Pollution Control Department data[321]
BOI by location Group A2 outside the EEC; extras in low-income provinces BOI guide 2026[319]
Talent A university with engineering and AI within an hour SUT, KKU (below)

On BOI terms, a high-efficiency data center (PUE 1.3 or lower, at least 2 MW of IT) is group A3 inside the EEC and A2 elsewhere.[319] Chaiyaphum, Ubon Ratchathani, Sa Kaeo, and Mukdahan are among the 20 lowest-income provinces; Nakhon Ratchasima, Khon Kaen, Saraburi, and Prachinburi are not.[319] In those provinces, A1 and A2 projects get a 50% cut in corporate income tax for five years after the exemption instead of three extra years, and the guide's table adds a double deduction of transport, electricity, and water costs for 10 years.[319] For a business whose biggest running cost is electricity, that deduction may be worth more than the tax holiday (our reading, to confirm with BOI). BOI is also mapping areas outside the EEC that have enough transmission capacity and are safe from floods and earthquakes.[322]

Chiang Mai falls short on most of these criteria. It is in seismic Zone 3, the highest band.[314] In October 2024 the Ping River rose about 1.08 m above the city's flood defenses.[29] The North had 129 days above the PM2.5 standard in 2024 and a 24-hour peak of 218 µg/m³, against 113 days and 129 µg/m³ in the Northeast.[321] Its wind is negligible: 0.02 GW for the Upper North,[307] and about 1% capacity factor in our model. Its solar is within about 5% of the best candidate, and it is cooler, with about 1,870 hours a year below 20 °C against about 670 at Sikhio (our model).

Wind: where Thailand has it

The older DEDE map put utility-grade wind only on the southern Gulf coast and at Doi Inthanon.[323] The JGSEE/KMUTT study compared four maps at 100 m and finds 17 GW of potential at a capacity factor of 20% or more with low-wind turbines, and 5 GW with conventional ones.[307] By region, the southern Gulf coast leads with 7.64 GW, the Lower Northeast (including Korat) has 1.66 GW, the Upper Northeast (including Chaiyaphum) 0.73 GW, and the Upper North 0.02 GW.[307]

Rank Sub-district (district, province) Potential at capacity factor 20%+ (MW)
2 Huai Bong (Dan Khun Thot, Nakhon Ratchasima) 168
5 Nong Waeng (Thepharak, Nakhon Ratchasima) 116
6 Non Ko (Sirindhorn, Ubon Ratchathani) 113
10 Wa Tabaek (Thep Sathit, Chaiyaphum) 96
11 Lam Phaya Klang (Muak Lek, Saraburi) 96
22 Lak Dan (Nam Nao, Phetchabun) 68
28 Don Mueang (Sikhio, Nakhon Ratchasima) 64
30 Nong Yang Suea (Muak Lek, Saraburi) 63

The ranking comes from JGSEE/KMUTT, Table 8.[307]

Farm Province, district MW In operation Operator
West Huay Bong 3 Nakhon Ratchasima, Dan Khun Thot 103.5 2012 Wind Energy Holding (WEH)[324][325]
West Huay Bong 2 Nakhon Ratchasima, Dan Khun Thot 103.5 2013 WEH[324][326]
T1, T2, T4 Nakhon Ratchasima, Thepharak 90 each T1 2018, T4 2019 WEH[324][327][328]
T3 Thepharak (Korat) and Thep Sathit (Chaiyaphum) 90 2018 WEH[324][329]
NKS Nakhon Ratchasima, Sikhio 90 2018 WEH[324][330]
Saranlom Nakhon Ratchasima, Dan Khun Thot 67.5 2018 Greenovation Power[328]
Mittraphap Nakhon Ratchasima, Sikhio 52.5 2018 Korat Wind Energy[328]
Lam Takhong phase 2 Nakhon Ratchasima, Sikhio and Pak Chong 24 2017 (planned) EGAT, with a wind-hydrogen pilot[331]
WTB Chaiyaphum, Thep Sathit 60 2016 WEH[324][332]
Chaiyaphum Wind Farm Chaiyaphum, Sap Yai 80 2016 EGCO[333]
Theppana Chaiyaphum, Thep Sathit 7.5 2013 EGCO[333]
Hanuman complex Chaiyaphum, incl. Thep Sathit 260 2018 to 2019 Energy Absolute[334][335][328]
Khao Kor Phetchabun, Khao Kho 60 2016 Khao Kor Wind Power[328]
WAYU (new) Chaiyaphum 78 not stated Gulf Development[336]

Theppana recorded plant factors of 18.8 to 21.1% from 2014 to 2017,[308] and RATCH expected each 103.5 MW West Huay Bong farm to deliver 175 million kWh a year,[309] about 19% by our arithmetic. The ERC assumes 24% for wind in the UGT2 portfolios[169] and BNEF 20% for 2024.[337] Our model, with a generic 4.2 MW low-wind turbine scaled to that range, gives about 21% for the Korat and Chaiyaphum cells, 14% for Muak Lek, and 1% for Chiang Mai (our estimate). Its cells are about 50 by 60 km, so the model ranks regions; only a measurement mast can size a turbine.

Korat and Chaiyaphum are the wind belt. The operating farms listed above in these two provinces add up to about 1.2 GW (our sum), on a strip about 90 km long from Lam Takhong north to Sap Yai (our measurement from published coordinates).[338][339]

The candidates compared

ID, site Province PV yield, kWh/kWp/yr (model) Wind capacity factor (model) Seismic zone Land, THB per rai km to Bangkok, straight line (est.) Grid Notes
C1 Sikhio, Lam Takhong corridor Nakhon Ratchasima 1,452 21% none about 300,000 (30-rai listing, 2024)[340] 170 EGAT 1,000 MW pumped storage in the district[341]; new 500/230 kV Korat 4 substation in the province[342] NKS and Mittraphap farms in the district; reservoir stress[316]
C2 Suranaree zone, SUT Nakhon Ratchasima 1,449 21% none 2.5M to 6M (search result only, not verified)[343] 223 City grid; 230 kV Korat 3 being expanded[342] Next to SUT; Korat flooded in 2010[344]
C3 Huai Bong, Dan Khun Thot Nakhon Ratchasima 1,484 21% none not found 186 Wind-farm lines (not verified) Best-ranked inland wind sub-district[307]
C4 Thep Sathit, Wa Tabaek Chaiyaphum 1,499 21% none about 129,000 (20-rai listing)[345] 209 500 kV Chaiyaphum 2 being expanded[342] Densest farms; lowest-income province[319]
C5 Muak Lek Saraburi 1,413 14% none about 350,000 (35-rai listing)[346] 125 500 kV Korat 4 to Wang Noi line crosses the province[347] INET-IDC3[348]; WHA estate growing[349]
C6 Khok Samrong Lopburi 1,471 18% none not found 150 Lopburi solar farm exports to EGAT[350] 30% of province low plain[351]; hottest site in the model
C7 Khon Kaen (KKU) Khon Kaen 1,482 18% none not found 390 not verified KKU H100 cluster[352]; INET-IDC4[353]; no ranked wind sub-district
C8 Sirindhorn Dam Ubon Ratchathani 1,422 8% none not found 554 EGAT dam (not verified) 45 MW floating solar[354]; 2019 floods[355]
C9 304 Industrial Park area Prachinburi 1,433 16% none estate price not found 119 893 MW in the estate[356] 344,000 m³/day water[356]; 20 m above sea level[357]
C10 Khao Kho Phetchabun 1,440 12% none not found 335 115 kV, 44.76 km to Lom Sak[358] Forest land[358]; coolest candidate
R1 Mae Hia (reference) Chiang Mai 1,418 1% Zone 3[314] not found 581 PEA 22/33 kV Ping floods[29]; worst haze region[321]
R2 Amata City (EEC reference) Chonburi 1,392 18% none 13.5M to 14.5M (data-center zone)[359] 72 Dense estate grid BOI A3 only[135]; listed 2 m above sea level[360]

Seismic zones follow the province lists of the 2021 regulation;[314] provinces it does not list are marked none. C1 and C2 share one wind cell. Treasury appraisals span everything from farmland to town centers (100 to 130,000 THB per square wah in Nakhon Ratchasima), so the table shows only listings.[361]

C1 Sikhio has farmland in a green (rural and agricultural) zone listed at about 300,000 THB per rai.[340] Korat's chamber of commerce pitches Sikhio's pumped storage, wind, and solar to data-center investors.[362] Suranaree University of Technology (about 17,000 students in 2020) is in Korat,[363] and Gorilla Technology says it has secured about 100 rai in Korat for a 200 MW AI campus (company claim).[364]

C4 Thep Sathit and Sap Yai has the highest solar yield, the densest wind farms, the cheapest land found, and the BOI terms of a lowest-income province. It is further from Bangkok and from a university, though, and no fiber route was found.

C5 Muak Lek is the closest wind area to Bangkok. INET's largest data center is in the province,[348] and WHA is adding almost 3,000 rai of estate land for future data centers.[349]

C7 Khon Kaen brings talent: KKU runs an H100 AI cluster and a BSc in AI,[352] and INET is building a 2,500 million THB data center there for the second quarter of 2027.[353]

C9, the 304 Industrial Park, offers estate power and water. In the October 2013 floods its operator expected the park to stay dry at 20 m above sea level (lowest point 13 m) behind a raised barrier.[357] It has no wind.

Five candidates did not make the shortlist. C3 Huai Bong is remote, and C4 offers the same wind belt with better BOI terms. C2 Suranaree has estate prices, C6 Lopburi is hot and lies on low plains, C8 Sirindhorn is far away and prone to floods, and C10 Khao Kho is forest land with a single 115 kV line.

How much of the power on-site solar, batteries, and wind can cover

Our model runs a flat 1.2 MW load (10,512 MWh a year) against hourly PVGIS solar and NASA POWER wind data, with a 4-hour battery at 90% round-trip efficiency. "Hourly" coverage is the share of the load met in the same hour by on-site plant, directly or through the battery; "annual" coverage is generation divided by use.

Mix per MW of IT Land, rai Hourly, C1 Sikhio Hourly, C4 Thep Sathit Hourly, R1 Chiang Mai Annual, C1
10 MWp PV, no battery 101 42% 42% 42% 138%
5 MWp PV, 10 MWh battery 51 63% 65% 62% 69%
10 MWp PV, 10 MWh battery 101 74% 74% 74% 138%
7.5 MWp PV, 20 MWh battery 76 90% 92% 88% 104%
10 MWp PV, 20 MWh battery 101 96% 96% 95% 138%
One 4.2 MW turbine only 6 52% 48% 2% 73%
10 MWp PV, 10 MWh battery, one turbine 108 95% 94% 76% 211%

The figures are our estimates from the model. Land is taken at 10.1 rai per MWp from the ERC filing[317] and at 1.5 rai per MW of wind from the operating footprint of Hanuman 9.[365]

Annual matching flatters solar. At Sikhio, 10 MWp makes 138% of the year's use yet covers only 42% of the hours. Google measures each data center's hourly match with carbon-free supply,[293] and Microsoft has committed to matching 100% of its use, 100% of the time, with zero-carbon purchases by 2030.[366] Ember, using hourly profiles, estimates that about a third of ASEAN data-center demand in 2030 could be met by solar and wind without batteries.[367][368] The battery does the work here: 20 MWh per MW of IT lifts 10 MWp from 42% to about 95%. Wind fills the nights. One turbine alone covers about half the hours in the belt, and almost none at Chiang Mai.

The catch is the surplus. The net-billing scheme approved on April 29, 2026 pays 2.20 THB/kWh for rooftop surplus, but only up to 5 kW per meter,[310] and commercial and industrial systems are normally built for zero export (installer guidance).[369] Our model therefore counts surplus as lost. At 10 MWp with 10 MWh, 44% of Sikhio's solar output is thrown away (our estimate).

What it costs

Input Value Source
Solar, installed 22.9M to 25.5M THB per MWp (USD 0.69M to 0.77M) BNEF Thailand 2024, USD 693,891 per MW[337]; Thai Solar Energy, 3,264.34M THB for 128.10 MW of ground-mounted plants incl. land and substations[370]
Wind, installed 53.7M THB per MW (USD 1.63M) BNEF Thailand 2024[337]; a single turbine costs more (our judgment)
Battery, 4 h, all-in 4.1M THB per MWh (USD 125 per kWh) Ember, markets outside China and the US, October 2025[371]
Grid power about 3,810 THB per MWh incl. Ft and VAT Our estimate from the PEA 22 to 33 kV time-of-use tariff for a 24/7 load[25]
UGT2 green power 4,323 to 4,708 THB per MWh incl. VAT EGAT rates from May 1, 2026[312]
Finance, life, land 8% cost of capital; 25 years solar and wind, 15 years battery; land at listing price Our estimates

The ranges that follow run from the low to the high solar cost. The cheapest mix at every candidate is 5 MWp with 10 MWh per MW of IT. It covers 62 to 65% of the load hour by hour at 3,083 to 3,424 THB per MWh of load, against 3,810 THB from the grid alone. At Sikhio it costs 3,240 to 3,356 THB (USD 98 to 102), which saves about 4.8 to 6.0 million THB (USD 145,000 to 182,000) a year per MW of IT after capital charges, for 171 to 184 million THB (USD 5.2 to 5.6 million) of plant and land. More coverage costs little more. With 7.5 MWp and 20 MWh, coverage reaches 88 to 92% at 3,189 to 3,664 THB, and with 10 MWp and 20 MWh it reaches 95 to 96% at 3,591 to 4,127 THB, about the grid cost. At Sikhio that larger plant and its land cost 342 to 368 million THB (USD 10.4 to 11.2 million), roughly as much as the building itself (all our estimates).

The sites differ little. Land is charged only where a price was found, and with one land price everywhere the cheapest mix spans only about 3,070 to 3,190 THB per MWh (at the low end of the solar cost) across all twelve sites (our extra run).

Wind does not pay on its own at this scale. One 4.2 MW turbine costs about 225 million THB (USD 6.8 million) at the BNEF farm price and is three and a half times the size of the load, so 28% of its output at Sikhio is lost. No mix with a turbine at any candidate comes below about 4,050 THB per MWh. At 2 MW of IT sharing one turbine, an extra run gives 86% coverage with 5 MWp and 10 MWh per MW of IT at 3,583 to 3,699 THB. That is slightly worse than a bigger battery without a turbine, since 7.5 MWp with 20 MWh gives 90% at 3,409 to 3,583 THB (our estimates). At this scale, then, wind is a hedge and does not lower the cost.

Sensitivity at Sikhio (our estimates, THB per MWh) 5 MWp + 10 MWh (63%) 10 MWp + 20 MWh (96%)
Base: battery USD 125 per kWh, land 300,000 THB per rai 3,240 to 3,356 3,840 to 4,071
Battery USD 73 per kWh (BNEF China turnkey 2025)[371] 3,016 to 3,132 3,393 to 3,625
Battery USD 192 per kWh (IRENA 2024 project average)[372] 3,528 to 3,643 4,415 to 4,647
Land 1M THB per rai 3,509 to 3,625 4,379 to 4,611
Land 14M THB per rai (Amata data-center zone) 8,514 to 8,630 14,389 to 14,621

The cheapest mix beats the grid in every case except on EEC land, where the model's best choice is no on-site plant at all. The battery price decides whether near-full coverage beats the grid too. Buying the uncovered 37% as UGT2 instead of grid power adds about 190 to 330 THB per MWh, so 5 MWp with 10 MWh plus UGT2 is green on an annual basis at about 3,430 to 3,690 THB per MWh at Sikhio, still below the all-grid price (our estimate, assuming UGT2 can cover part of a load). If the separate data-center tariff of 5 to 6 THB/kWh now under consideration is adopted, every on-site mix gains.[134]

Rules for generating power on site and buying green power

Topic What applies
Generation license Below 1,000 kVA per source only a notification (since Apr 4, 2025); from 200 kVA also a controlled-energy license (Phor Kor 2); above 1,000 kVA an ERC license[373][374]
Factory license Rooftop and building solar freed in December 2024; ground-mounted and floating not affected, so a ground array is a Class 3 factory, kept 100 m from schools, temples, hospitals and government offices; the ERC issues the license (Ror Ngor 4) for DIW[375][376][377]
Environment ERC Code of Practice (CoP) report, not a full EIA; a 5.001 MWp array in Lampang filed one and held a public hearing in 2025; wind farms need no EIA[378][317][365]
Land reform land Court ruled a wind farm on Sor Por Kor land a misuse (2016); a 2017 order lets the land-reform office approve energy uses[379]
Direct PPA 2,000 MW pilot for new solar and wind over the grid; data centers need BOI promotion, 50 MW of IT per building and a 10-year plan[172][311]
Draft wheeling charges Medium voltage 1.9110 THB/kWh plus 0.4978 system security plus 0.1447 policy; surplus beyond schedule goes to the utility unpaid[380]
UGT1 Normal tariff plus Ft plus 0.0375 THB/kWh (2026), with I-RECs from state-owned plants[167]
UGT2 4.0423 to 4.3969 THB/kWh before VAT from May 1, 2026 by portfolio and voltage; 100% specified green supply for large users; 10-year contracts[312][169][313]
I-RECs Thai solar and wind certificates fell to USD 0.55 per MWh (about 18 THB) by December 2025[381]

Direct PPA is moving but does not fit this project. The National Energy Policy Council extended it to industrial users on July 15, 2026, with the final wheeling charges still outstanding in August,[165] and the minister said on August 28 that the 2,000 MW cap had been lifted.[382] Even so, the draft medium-voltage adders total 2.55 THB/kWh, which with solar at about 2.16 THB/kWh (the minister's figure)[382] puts delivered power near 4.7 THB/kWh, above UGT2 (our arithmetic). UGT2 has also fallen from 4.5475 THB/kWh in its 2024 design.[169] A 1.2 MW load is a PEA large general service customer (1,000 kW and above),[25] which is the class of large user that UGT2 is meant for.[313]

Three policy moves matter. The ERC consulted from September 19 to October 18, 2026 on a Data Center Electricity Distribution License, whose applicants would file a supply plan by source, self-generation included, and an RE100 target year.[383] On September 4, 2026 the policy board paused 166 projects, 49 under construction and 117 awaiting permits, and will reconsider regulating data centers above 2 MW of demand as factories.[315] And data-center requests to PEA and MEA total about 35,000 MW against about 8,800 MW in the draft PDP2026, while EGAT studies backup charges for self-generators.[384]

Grid, water, and hazards

Grid

EGAT's June 2026 tender covers a new 500/230 kV Nakhon Ratchasima 4 substation and expansions of the 500 kV Chaiyaphum 2 and 230 kV Nakhon Ratchasima 3 substations,[342] and in May 2025 EGAT awarded a 1.46 billion THB voltage-support (STATCOM) contract at Chaiyaphum 2.[385] The ERC approved a 500 kV route from Korat 4 to Wang Noi through Saraburi to carry renewable power from the Northeast to Bangkok.[347] EGAT's Lam Takhong pumped-storage plant in Sikhio has 1,000 MW.[341] Substation sites were not published, and outside estates a 115 kV customer co-invests in the line.[290]

Water

Lam Takhong held only 16% on May 3, 2025,[316] and Korat's chamber of commerce plans talks with the provincial irrigation office about supplying data centers.[362] The 304 estate offers 344,000 m³ a day,[356] and WHA has already contracted 30 million m³ a year to data-center customers.[386] A closed-loop design with dry coolers, as in option B, keeps the need small (our judgment).

Floods

Floods in October 2010 hit 21 provinces, including Nakhon Ratchasima, Chaiyaphum, Saraburi, Prachinburi, and Khon Kaen.[344] In September 2019, 994 villages in 13 districts of Ubon Ratchathani flooded,[355] and in 2011 seven industrial estates stood under up to 3 m of water.[387] The Sikhio plot lies at about 260 m.[340] We did not retrieve flood maps for individual parcels.

Earthquakes

The 2021 regulation[320] puts Chiang Mai and other northern and western provinces in Zone 3, and Bangkok and the lower central provinces in Zone 2. Nakhon Ratchasima, Chaiyaphum, Saraburi, Khon Kaen, and Prachinburi are not listed.[314]

Haze and heat

In 2024 the North had 129 days above the PM2.5 standard, the Northeast 113, and the Central region 101.[321] On February 23, 2026 the Northeast had the day's highest reading, 84.9 µg/m³, with Khon Kaen, Saraburi, and Prachin Buri among the provinces to monitor.[388] Korat is warmer than Chiang Mai (a mean of 26.3 against 23.3 °C in our model), which matters little with warm-water liquid cooling.

Ranked shortlist

Rank Site Why Main risk
1 Sikhio / Lam Takhong corridor, Nakhon Ratchasima Inside the wind belt with farms in the district; EGAT pumped storage and a new 500 kV node in the province; 170 km to Bangkok; no seismic zone; SUT; provincial interest Water (Lam Takhong at 16%); land at about 300,000 THB per rai
2 Thep Sathit / Sap Yai, Chaiyaphum Highest solar yield, densest wind farms, cheapest land, lowest-income-province BOI terms, 500 kV Chaiyaphum 2 Remote: thin talent pool, fiber unverified, 209 km to Bangkok
3 Muak Lek, Saraburi Closest wind area to Bangkok (125 km); new 500 kV corridor; INET and WHA data-center ecosystem Weaker wind and the most expensive farmland listed; no BOI area bonus
4 Khon Kaen KKU AI cluster and degree; INET-IDC4 as neighbor or partner; high solar yield No proven wind; 390 km to Bangkok
5 304 Industrial Park, Prachinburi Estate power and water, flood defense, 119 km to Bangkok, outside the EEC No wind; estate land makes 100 rai of solar costly

We checked the ranking against the model. The model keeps the top two on top for wind (21% each) and puts Thep Sathit slightly ahead on cost (3,118 to 3,234 against 3,240 to 3,356 THB per MWh for the cheapest mix), thanks to more sun and cheaper land. We keep Sikhio first for grid, distance, and talent, which the model does not weigh. The model would swap places 3 and 4: Muak Lek has the weakest wind cell on the list (14%) and the highest cost of any candidate (3,308 to 3,424 THB), while Khon Kaen's cell shows 18% at 3,084 to 3,200 THB. We keep Muak Lek third for its short distance to Bangkok and its data-center neighbors, and because Khon Kaen's 18% comes from a coarse cell with no ranked sub-district or farm behind it. At one land price the shortlist sits within about 4% on energy cost, so wind, grid, water, and people set the order.

What this means for the investor

What follows is our judgment.

The search should focus on the Korat and Chaiyaphum belt. A parcel of 100 to 150 rai per MW of IT carries 5 to 10 MWp of solar and a 10 to 20 MWh battery, which covers roughly two thirds to nearly all of the power hour by hour at or below the grid price, and UGT2 covers the rest. Chiang Mai's sun is nearly as good, but its earthquake zone, floods, haze, and lack of wind count against it.

Solar should be sized to the battery rather than to the annual total. Because surplus cannot be exported, panels beyond about 5 MWp per MW of IT pay only with more storage, and the battery price decides whether 95% coverage beats the grid.

Wind on site makes sense only with a partner. One turbine does not pay at 1 MW of IT. At 2 MW or more, it is worth testing if a developer in the belt (WEH, EGCO, Energy Absolute, or Gulf) will build or share a turbine, a mast confirms the wind, and the land title allows it.

CMU ITSC remains the pilot. Option A stays the first step, and the choice of site matters once anchor load nears the 2 MW BOI threshold.

The policy pause and water need watching. The September 2026 pause and the proposed license could change where and how data centers connect, and water is the open point in Korat.

Open questions

Question Whom to ask
Spare capacity, voltage, lead time and co-investment for 2.5 to 5 MW at a Sikhio or Thep Sathit parcel; nearest node to Korat 4 and Chaiyaphum 2 PEA's Northeastern regional office for Nakhon Ratchasima and Chaiyaphum; EGAT transmission planning (connection inquiry)
Is the ground-mounted solar factory license still required, and does the 100 m setback hit the parcel? Department of Industrial Works; the ERC one-stop service
Generation license, CoP and hearing; does on-site solar fall under the proposed data-center distribution license? Office of the ERC
Does A2 combine with the lowest-income-province 50% reduction and the double deduction of electricity cost in Chaiyaphum; is a phased build to 2 MW accepted? BOI, including its regional office in Nakhon Ratchasima
Title type (chanote, Nor Sor 3 Kor, Sor Por Kor), zoning color and whether a solar farm is allowed Provincial land offices; provincial Public Works and Town and Country Planning offices
Water rights and allocation from Lam Takhong or other sources Royal Irrigation Department, provincial irrigation office in Nakhon Ratchasima
Diverse fiber routes and latency to Bangkok from each parcel NT, 3BB, AIS (and INET for its dark fiber)
Wind at hub height on the parcel, and turbine partnership terms A 12-month measurement mast; WEH, EGCO, Energy Absolute, Gulf
When will the policy board publish its location and water rules, and are new projects affected? Data-center policy board secretariat; BOI
Can UGT2 cover only the hours on-site plant misses, and at what PEA (not EGAT) rate? PEA; Office of the ERC